Pemberton Lane Guesthouse · courtyard and garden works

14 Pemberton Lane, Bangalow NSW 2479 · Contract UL-C-2026-014 signed 20/02/2026 · Site start 09/06/2026 · Project manager Sian Mackie · Contract administrator Kirra Ashby, Halyard Studio

As at 04/09/2026 08:12 · last diary entry 04/09/2026 08:12 by T. Reardon · programme rev 3

Contract sumA$288,640inc GST · 262,400 ex
Revised contract sumA$273,810ex GST · +11,410 variations
Claimed to dateA$184,185certified ex GST · 4 claims
Paid to dateA$106,308.95inc GST · 3 claims paid
Retention heldA$13,120at the 5 percent cap
Days to practical completion54forecast 28/10/2026
Rain days used7 of 12allowed · 13 EOT days in all

Timeline

Programme rev 3, issued 02/09/2026 · 13 working days extension approved (7 rain, 6 variations) · practical completion 09/10/2026 to 28/10/2026

Stage
MarAprMayJunJulAugSepOctNovDecJan 2027
Done
Milestones and rain days
7 rain
100%
100%
100%
100%
100%
55%
12%
0%
0%
  • Contract programme
  • Work done
  • Forecast
  • Milestone
  • Rain day
  • Today
  • Click a stage to see which claims paid for it

Stage dates, progress and value are listed in the stage table that follows.

Stages: contract programme, actual or forecast dates, site progress, certified progress and value
No.StageProgrammeActual or forecastSite doneCertifiedValue ex GSTCertified to dateTo comeStatus
1Design and approvalsDA 10.2026.118.1 approved 22/05/2026. Drawings L-01 to L-14 rev C issued for construction 05/06/2026.02/03 to 29/0502/03 to 05/06+7 d100%100%18,40018,4000Complete
2Site establishment and demolitionFencing, silt control, removal of the old pool surround and the concrete path.09/06 to 19/0609/06 to 19/06on time100%100%14,20014,2000Complete
3Drainage and earthworksThree rain days (24/06, 25/06, 14/07). Additional agricultural drain behind the north wall raised as VO-02.22/06 to 10/0722/06 to 15/07+5 d100%100%31,60031,6000Complete
4Retaining walls and structureSandstone block in place of timber sleepers (VO-01, four days). Engineer signed off the north wall 21/08/2026.13/07 to 07/0816/07 to 21/08+14 d100%100%58,90058,9000Complete
5Paving, decking and stepsComplete 02/09/2026. Certified at 85 percent in PC-04 (steps not grouted at 31/08); the balance falls into PC-05.27/07 to 21/0803/08 to 02/09+12 d100%85%47,30040,2057,095Complete
6Irrigation and lightingMainline and zones 1 to 4 in. Controller and bollard fittings follow the lighting selection (awaiting your sign-off).17/08 to 04/0924/08 to 18/09+14 d55%30%22,8006,84015,960In progress
7Soil preparation, planting and turfRear beds planted 03/09. Groundcover stock arrives from 21/09, turf 05/10.31/08 to 02/1031/08 to 16/10+14 d12%5%52,6002,63049,970In progress
8Practical completion and handoverDefects walk, final clean, as-built drawings, maintenance manual, half of retention released.06/10 to 09/1019/10 to 28/10+19 d0%0%8,60008,600Not started
9Establishment maintenance (13 weeks)Weekly visits, replacement of failed stock, balance of retention released at the end.12/10 to 08/0129/10 to 27/01+19 d0%0%8,00008,000Not started
Contract stages262,400172,77589,625
Approved variations VO-01, VO-02, VO-03+11,41011,4100
Revised contract sum, ex GST273,810184,18589,625

Site done is what Tom has recorded on the ground as at 04/09. Certified is what has been assessed in a payment claim to 31/08. The gap between them is work done this fortnight, and it will appear in PC-05 for the period to 30/09. Milestones: contract signed 20/02, deposit paid 27/02, DA 10.2026.118.1 approved 22/05, site start 09/06, practical completion forecast 28/10, defects and establishment period to 27/01/2027.

Progress claims

Certified by K. Ashby, Halyard Studio, contract administrator · payment due 15 business days after a claim is served (Building and Construction Industry Security of Payment Act 1999, NSW) · retention 10 percent of each claim to a cap of 5 percent of the contract sum

Progress claim ledger. Each claim row expands to its stage breakdown.
ClaimPeriodStagesClaimed ex GSTCertified ex GSTRetentionGSTPayable inc GSTDueStatus
Deposit on signingServed 24/02/2026 · certified 24/02/2026S113,120.0013,120.000.001,312.0014,432.0017/03/2026Paid 27/02

PC-01 · stage breakdown

Certified 13,120.00 ex GST · less retention 0.00 · net 13,120.00 · GST 1,312.00 · payable 14,432.00 inc GST

LineStage or variationValue ex GSTCompleteValue to datePreviously certifiedThis claim
S1Design and approvals18,40071%13,120.000.0013,120.00
Total certified this claim13,120.00

Five percent deposit under clause 7.1, credited against the design stage. No retention on the deposit.

Period to 30/06/2026Served 01/07/2026 · certified 08/07/2026S1, S2, S338,440.0038,440.003,844.003,459.6038,055.6022/07/2026Paid 20/07

PC-02 · stage breakdown

Certified 38,440.00 ex GST · less retention 3,844.00 · net 34,596.00 · GST 3,459.60 · payable 38,055.60 inc GST

LineStage or variationValue ex GSTCompleteValue to datePreviously certifiedThis claim
S1Design and approvals18,400100%18,400.0013,120.005,280.00
S2Site establishment and demolition14,200100%14,200.000.0014,200.00
S3Drainage and earthworks31,60060%18,960.000.0018,960.00
Total certified this claim38,440.00
Period to 31/07/2026Served 03/08/2026 · certified 11/08/2026S3, S4 · VO-01, VO-0254,365.0054,365.005,436.504,892.8553,821.3524/08/2026Paid 21/08

PC-03 · stage breakdown

Certified 54,365.00 ex GST · less retention 5,436.50 · net 48,928.50 · GST 4,892.85 · payable 53,821.35 inc GST

LineStage or variationValue ex GSTCompleteValue to datePreviously certifiedThis claim
S3Drainage and earthworks31,600100%31,600.0018,960.0012,640.00
S4Retaining walls and structure58,90055%32,395.000.0032,395.00
VO-01Replace timber sleeper retaining wall with sandstone block, north wall+9,85060%5,910.000.005,910.00
VO-02Additional agricultural drain and geofabric behind north wall (seepage found at excavation)+3,420100%3,420.000.003,420.00
Total certified this claim54,365.00
Period to 31/08/2026Served 01/09/2026 · certified 02/09/2026S4, S5, S6, S7 · VO-01, VO-0380,625.0078,260.003,839.50 capped7,442.0581,862.5522/09/2026Certifieddue 22/09

PC-04 · stage breakdown

Certified 78,260.00 ex GST · less retention 3,839.50 · net 74,420.50 · GST 7,442.05 · payable 81,862.55 inc GST

LineStage or variationValue ex GSTCompleteValue to datePreviously certifiedThis claim
S4Retaining walls and structure58,900100%58,900.0032,395.0026,505.00
S5Paving, decking and steps47,30085%40,205.000.0040,205.00
S6Irrigation and lighting22,80030%6,840.000.006,840.00
S7Soil preparation, planting and turf52,6005%2,630.000.002,630.00
VO-01Replace timber sleeper retaining wall with sandstone block, north wall+9,850100%9,850.005,910.003,940.00
VO-03Delete turf to rear service yard, substitute decomposed granite−1,860100%−1,860.000.00−1,860.00
Total certified this claim78,260.00

Paving was claimed at 90 percent (A$42,570) and certified at 85 percent (A$40,205): the steps were not grouted at 31/08. The A$2,365 difference is carried into PC-05, not lost. Retention on this claim is capped at the 5 percent limit.

Totals4 claims186,550.00184,185.0013,120.0017,106.50188,171.50
Original contract sum262,400ex GST
Approved variations+11,410VO-01, VO-02, VO-03
Revised contract sum273,810ex GST · 301,191.00 inc GST
Balance to complete89,625revised sum less certified to date
Certified to date184,185ex GST · 67 percent of the revised sum
Retention held13,120cap reached at PC-04
Paid to date106,308.95inc GST · PC-01 to PC-03
Outstanding81,862.55inc GST · PC-04 due 22/09/2026

Retention is taken off before GST, so GST is charged on the net amount payable. At practical completion half the retention (A$6,560) is released with the PC claim; the balance is released at the end of the 13 week defects and establishment period, 27/01/2027.

Variations register

Priced before any work starts · approved in writing by you · terracotta on this board always means a variation, not the contract

Variations register
No.DescriptionTimeStatus
VO-01Replace timber sleeper retaining wall with sandstone block, north wallClient request29/06/2026+9,850+4 dApproved 07/07
VO-02Additional agricultural drain and geofabric behind north wall (seepage found at excavation)Latent condition14/07/2026+3,420+2 dApproved 21/07
VO-03Delete turf to rear service yard, substitute decomposed graniteClient request04/08/2026−1,860noneApproved 10/08
VO-04Outdoor kitchen bench slab, plumbing and power rough-inClient request25/08/2026+14,600+6 dAwaiting your approval · 10 days
VO-05Upgrade 12 tuckeroo from 45 L to 100 L stockContract administrator suggestion02/09/2026+2,760noneQuoted
VO-06Additional lighting circuit to the arbourClient request20/08/2026+1,940+1 dDeclined 28/08
ApprovedVO-01, VO-02, VO-03 · added to the contract sum+11,410+6 d
PendingVO-04 awaiting approval, VO-05 quoted · not in any total until you approve+17,360+6 d

Site diary

Entered daily by T. Reardon, site supervisor · rainfall from the site gauge to 9 am, checked against BOM Ballina Airport AWS · a rain day is 10 mm or more, or the site declared unworkable

Recent diary entries, oldest first
DateWeatherRainCrewPlant on siteWork performedDeliveriesInspections and visitors
Thu 20/08/2026Fine · 21°0 mm61.7 t excavator, plate compactor, tile sawSandstone capping to the north wall complete. Bluestone paving to courtyard bays 3 to 5 on re-screeded bedding.Bluestone pavers 24 m2 (Northern Stone Supplies)none
Fri 21/08/2026Fine · 22°0 mm6Tile saw, plate compactorRetaining walls complete and cleaned down. Paving bays 5 to 7. Formwork for the garden steps.noneStructural engineer final inspection of the north wall, signed off (M. Tran, Rivergate Consulting)
Mon 24/08/2026Cloudy · 19°2 mm7Trencher, tile sawIrrigation mainline trenched along the west path. Paving bays 8 and 9. Two from the irrigation subcontractor on site.Irrigation pipe, valves and fittings (Coastal Irrigation Supplies)none
Tue 25/08/2026Fine · 23°0 mm7TrencherIrrigation laterals to zones 1 to 3. Deck bearers and joists set. VO-04 quotation issued to the client.Spotted gum decking 38 m2none
Wed 26/08/2026Fine · 24°0 mm6noneDeck boards to the dining terrace. Sandstone step treads set, sample finish approved on site.noneLandscape architect site visit, step finish approved (K. Ashby, Halyard Studio)
Thu 27/08/2026Showers · 20°6 mm6TrencherLight showers to 9 am, below the 10 mm threshold, worked through. Lighting conduit and pits to the path and arbour. Deck boards continue.noneElectrician rough-in inspection, lighting circuits 1 and 2
Fri 28/08/2026Fine · 22°0 mm5noneDecking complete. Steel edging to the garden beds. Client walk-through; VO-06 declined on site.noneClient walk-through with R. Pemberton and S. Mackie
Mon 31/08/2026Fine · 21°0 mm61.7 t excavator, skid steerSoil preparation starts. Rear beds excavated to 400 mm, gypsum spread, garden mix placed to beds A and B.Garden mix 18 m3 (first of three loads)none
Tue 01/09/2026Rain · 17°Rain day 72Submersible pumpNo productive work. Rain day declared 7 am. Irrigation trenches pumped out, site secured. PC-04 served today.Garden mix load 2 deferred to 02/09none
Wed 02/09/2026Cloudy · 19°1 mm6Skid steerSteps grouted, paving complete. Garden mix to beds C and D. Advanced stock unloaded and set out.Garden mix 18 m3. Golden penda 3 x 45 L, lilly pilly 46 x 300 mm, native gardenia 5 x 300 mm (Hinterland Advanced Trees)none
Thu 03/09/2026Fine · 22°0 mm7Skid steerLilly pilly hedge planted (46), staked and watered in. Bower of beauty planted to the arbour posts (6). Irrigation zone 4.Hardwood mulch 12 m3none
Fri 04/09/2026Fine · 23°0 mm6Skid steerPlanting continues, golden penda and native gardenia to the front beds. Irrigation controller install. Entry made 08:12, will be completed at close of day.None expectednone
Rain days declared on this project
DateWeatherRainCrewPlant on siteWork performedDeliveriesInspections and visitors
Wed 24/06/2026Rain · 15°Rain day 121.7 t excavator (idle)No productive work. Excavation for the stormwater line flooded; pumped out and site secured.nonenone
Thu 25/06/2026Rain · 16°Rain day 221.7 t excavator (idle)No productive work. Trench walls slumped on the east side, re-cut on 26/06.Drainage aggregate deferred to 26/06none
Tue 14/07/2026Rain · 14°Rain day 32noneNo productive work. Subgrade too wet to compact; proof roll failed at 2 pm.nonenone
Tue 04/08/2026Rain · 17°Rain day 42noneNo productive work. Heavy rain from 3 am, courtyard subgrade under water; silt fence checked and repaired.Bluestone pavers deferred to 06/08none
Wed 05/08/2026Showers · 18°Rain day 53Submersible pumpSite pumped out and drying. No paving or wall work possible; stone protected under cover.nonenone
Wed 19/08/2026Rain · 16°Rain day 62noneNo productive work. Paving bedding sand washed; re-screeded 20/08.nonenone
Tue 01/09/2026Rain · 17°Rain day 72Submersible pumpNo productive work. Rain day declared 7 am. Irrigation trenches pumped out, site secured. PC-04 served today.Garden mix load 2 deferred to 02/09none

7 rain days declared of 12 allowed202 mm across those dayseach rain day is one working day added to the date for practical completion

Diary entries with an inspection or visitor
DateWeatherRainCrewPlant on siteWork performedDeliveriesInspections and visitors
Wed 08/07/2026Fine · 19°0 mm51.7 t excavator, plate compactorStormwater and agricultural lines laid to the rear beds, bedded and inspected before backfill.Drainage aggregate 6 m3Hydraulic consultant inspected drainage before backfill (J. Malouf, Rivergate Consulting)
Mon 20/07/2026Fine · 18°0 mm61.7 t excavator, concrete pumpFootings poured for the north wall after inspection; sleeper wall removed to the west boundary.Concrete 9 m3, N12 reinforcementStructural engineer inspected north wall footings before pour (M. Tran, Rivergate Consulting)
Fri 21/08/2026Fine · 22°0 mm6Tile saw, plate compactorRetaining walls complete and cleaned down. Paving bays 5 to 7. Formwork for the garden steps.noneStructural engineer final inspection of the north wall, signed off (M. Tran, Rivergate Consulting)
Wed 26/08/2026Fine · 24°0 mm6noneDeck boards to the dining terrace. Sandstone step treads set, sample finish approved on site.noneLandscape architect site visit, step finish approved (K. Ashby, Halyard Studio)
Thu 27/08/2026Showers · 20°6 mm6TrencherLight showers to 9 am, below the 10 mm threshold, worked through. Lighting conduit and pits to the path and arbour. Deck boards continue.noneElectrician rough-in inspection, lighting circuits 1 and 2
Fri 28/08/2026Fine · 22°0 mm5noneDecking complete. Steel edging to the garden beds. Client walk-through; VO-06 declined on site.noneClient walk-through with R. Pemberton and S. Mackie

Plant schedule

Per drawing L-11 rev C · 14 lines, 719 plants and 185 m² turf · substitutions are like for like, same pot size, approved by the contract administrator before delivery

Plant schedule
PotNurseryOrderedStatus
Cupaniopsis anacardioidesTuckerooVO-05 (upgrade to 100 L) is quoted; order held at 45 L until you decide45 L12Hinterland Advanced Trees, Clunes10/08/202614/09/2026Ordered
Waterhousea floribundaWeeping lilly pilly45 L8Hinterland Advanced Trees, Clunes10/08/202614/09/2026Ordered
Xanthostemon chrysanthusGolden pendaDelivered 02/09, planting 04/0945 L3Hinterland Advanced Trees, Clunes10/08/202602/09/2026Delivered
Buckinghamia celsissimaIvory curl45 L2Hinterland Advanced Trees, Clunes10/08/202614/09/2026Ordered
Atractocarpus fitzalaniiNative gardeniaDelivered 02/09, planting 04/09300 mm5Hinterland Advanced Trees, Clunes10/08/202602/09/2026Delivered
Syzygium australe 'Aussie Boomer'Lilly pilly hedgePlanted 03/09 to the rear boundary300 mm46Coastal Natives Wholesale, Alstonville17/08/202602/09/2026Planted
Pandorea jasminoidesBower of beautyPlanted 03/09 to the arbour posts200 mm6Coastal Natives Wholesale, Alstonville17/08/202602/09/2026Planted
Banksia spinulosaHairpin banksiaStraight species not available in 300 mm this season. Banksia spinulosa 'Birthday Candles' approved by K. Ashby 01/09, same pot, no price change300 mm9Coastal Natives Wholesale, Alstonville17/08/202621/09/2026Substituted
Westringia fruticosa 'Grey Box'Coastal rosemary200 mm38Coastal Natives Wholesale, Alstonville17/08/202621/09/2026Ordered
Lomandra longifolia 'Tanika'Mat rush140 mm220Coastal Natives Wholesale, Alstonville17/08/202621/09/2026Ordered
Dianella caerulea 'Little Jess'Flax lily140 mm160Coastal Natives Wholesale, Alstonville17/08/202621/09/2026Ordered
Viola banksiiNative violet140 mm120Coastal Natives Wholesale, Alstonville24/08/202628/09/2026Ordered
Doodia asperaRasp fernShade beds under the deck140 mm90Coastal Natives Wholesale, Alstonville24/08/202628/09/2026Ordered
Stenotaphrum secundatum 'Sir Walter'Buffalo turf185 m2, laid the day it is cutRoll185Ballina Turf Supplies, Ballina31/08/202605/10/2026Ordered

Showing all 14 lines

Documents and approvals

Everything you have signed, everything we are insured for, and the 2 items waiting on you

  • VO-04 · Outdoor kitchen bench slab, plumbing and power rough-in · A$14,600 ex GST, six working daysSent 25/08/2026Awaiting youAsk a question
  • Lighting selection · bollard finish, bronze or charcoal, drawing L-12 detail 4 · needed by 11/09/2026 to hold the fitting deliverySent 27/08/2026Awaiting youAsk a question
  • Contract UL-C-2026-014, signed 20/02/2026Executed 20/02/2026PDF · 2.4 MB
  • Landscape drawings L-01 to L-14, rev C, issued for constructionIssued 05/06/2026PDF · 18.7 MB
  • Specification, rev BIssued 05/06/2026PDF · 1.1 MB
  • Programme rev 3 (revised for EOT days 1 to 13)Issued 02/09/2026PDF · 240 KB
  • Payment schedule PC-04 (K. Ashby, Halyard Studio)Issued 02/09/2026PDF · 96 KB
  • DA 10.2026.118.1 notice of determination, Byron Shire CouncilApproved 22/05/2026PDF · 640 KB
  • Public liability, A$20,000,000, certificate of currencyExpires 31/03/2027
  • Contract works insurance, Pemberton Lane projectExpires 30/04/2027
  • Workers compensation, icare NSW, certificate of currencyExpires 30/06/2027
  • Contractor licence 348216C, structural landscaping, NSW Fair TradingRenews 14/11/2027

Project managerSian Mackie, Understory · 0427 118 402 Site supervisorTom Reardon, Understory · 0419 774 236 Contract administratorKirra Ashby, Halyard Studio · 02 6687 0140
Understory Landscapes · Bangalow NSW ABN61 834 290 061 Licence348216C · structural landscaping, NSW Fair Trading